In Carolina Park, the Pizza Place Opened Faster Than the Ball Field

In Carolina Park, the Pizza Place Opened Faster Than the Ball Field

  • September 24, 2026

"It's a big day for the recreation department and all the stuff that's going to be out here with a baseball field, softball fields, all kinds of stuff that's going to be out here," Steve Gergick, then the Town of Mount Pleasant's recreation director, told a small crowd at a groundbreaking on September 27, 2022.

He was talking about Phase III of the Carolina Park Recreation Complex, the fields and courts everyone in the neighborhood had been told were coming next to Cario Middle School. The town's contractor estimated the project would cost about $10 million and wrap up by fall of 2023.

It finished this past February. Two and a half years past the projection, and about seventeen years after the original master plan was even drawn up.

In that same window this year, two brand-new businesses signed leases, built out empty spaces, and opened their doors in Carolina Park in a fraction of that time. A pizza place did it in months. So did a golf cart dealership. That gap says something real about how this neighborhood actually grows, and it is worth understanding if you live here and have ever wondered why the thing the town promised always seems to land later than the thing a business just decided to build.

What Fall 2023 Was Supposed to Look Like

The Recreation Complex traces back to a master plan SeamonWhiteside completed in 2009. Phase I opened in 2010 with four lighted multipurpose fields. Phase II, mostly plumbing and site infrastructure, didn't finish until 2019. When the town broke ground on Phase III in 2022, the plan called for two new rectangular fields for football, rugby, and lacrosse, two baseball and softball diamonds, two outdoor courts lined for basketball and pickleball, a dog park, and more parking.

By the time SeamonWhiteside's Whitner Kane spoke to a reporter about the finished complex, the price tag had settled at $7.8 million rather than the $10 million first floated at groundbreaking, and the amenity list read: baseball and softball fields, batting cages, pickleball and basketball courts, a dog park, a pond, and nature trails. Kane's read on why it took as long as it did was straightforward. "Mount Pleasant's grown significantly since 2009, especially in recreation," she said, and scheduling and adding fields had simply become a constant, ongoing priority rather than a project with a fixed end date.

Even that account wasn't the true finish line. The Cario Baseball Field, the piece sitting right against Cario Middle School with its own artificial turf, dugouts, sports lighting, and restroom building, didn't open until a ribbon-cutting this February. Councilmembers Jake Rambo, Howard Chapman, and Daniel Brownstein were there. The middle school band played the anthem.

Milestone Date
Recreation Complex master plan completed 2009
Phase I opens (four lighted multipurpose fields) 2010
Phase II completes 2019
Phase III groundbreaking, fall 2023 finish projected September 2022
Pickleball courts, dog park, batting cages complete reported late 2025
Cario Baseball Field ribbon-cutting February 2026

Seventeen years from first drawing to last ribbon. That is the pace a public recreation project moves at when it depends on capital improvement budgets and special revenue funds arriving in the right sequence.

The Businesses That Got There First

Compare that to Steel City Pizza, which opened in the Carolina Park corridor in April. The build was a 3,892-square-foot interior upfit inside an existing shell space, handled by Charles Blanchard Construction Corp, a firm that has now completed 110 restaurant projects across the region. A commercial kitchen, dining room, bar, and back-of-house went in on a schedule tight enough that the crew called out the coordination of specialized kitchen equipment as one of the harder parts of the job. It still opened on time for April.

Two months after that, Botero Carts opened at 1161 Highway 41, its first Lowcountry location and only the second in South Carolina. It's a family-owned dealership that sells and services lithium-ion electric golf carts under brands like Evolution, Dach, Bintelli, and TEKO. Mayor Will Haynie and Chamber of Commerce Director Rebecca Imholz showed up for that ribbon-cutting too, alongside General Manager Jim Putzel.

Neither business took years. Neither needed a town council vote or a multi-phase funding plan. A landlord had a space, a company decided to fill it, and a few months later the doors were open.

Why the Math Works Out That Way

None of this is a knock on the town's process. A recreation complex serving every kid's rec league in north Mount Pleasant has to answer to public budgeting cycles, competitive bidding, and the reality that funding for four fields at once rarely shows up in a single fiscal year. That is the tradeoff for building something the whole neighborhood shares and nobody has to pay a membership fee to use.

A restaurant or a cart dealership only answers to a landlord and a lender. That is the tradeoff for something one business owns outright, which is also why it can close, change hands, or expand on a schedule nobody votes on.

Carolina Park in 2026 is a live example of both clocks running side by side. The public clock just finished a project that started before some of the kids playing on the new field were born. The private clock turned over two storefronts in the same four-month stretch it took the town to cut one ribbon.

What an Actual Week Looks Like Now

For a resident, the practical effect shows up in small, specific ways this year:

  • A weeknight practice at the Cario Baseball Field now happens under real sports lighting for the first time, instead of daylight-only scheduling.
  • A Friday dinner run can go to Steel City Pizza instead of driving out of the neighborhood.
  • A golf cart battery or service issue no longer means a trip out of the Lowcountry, since Botero Carts is now the closest dealership carrying that inventory.
  • Costco, CVS, and the Wando Mount Pleasant Library remain the errands that haven't changed, the same anchors that have been there for years.
  • Riverside residents still have The Lake Club, the private pool and pavilion overlooking Bolden Lake that opened back in 2021, a reminder that developer-built amenities inside a single community can move on their own faster timeline entirely.

None of that required a real estate transaction to notice. It's just what changed on the ground this year.

The Next Piece Is Already Filed

If the pattern holds, more of this is coming, and probably not from the town's side. In July, the developer behind Carolina Park applied for a stormwater permit to build three more barn-style monument signs on about 1.3 acres along Highway 17 at Darrell Creek Trail, signage meant to advertise still more commercial tenants inside the neighborhood. Clearing and grading for those signs is a matter of a permit and a contractor, the same private-sector clock that got Steel City Pizza and Botero Carts open in a season each.

The ball field took seventeen years end to end. The two businesses that opened in the same stretch of 2026 took a few months apiece. If you're waiting on the next public amenity in Carolina Park, plan around the slow clock. If you're wondering what's opening next in a storefront, the fast one is worth watching more closely.

If you're curious how a neighborhood like this keeps changing shape, quarter by quarter, Katherine Cox + Co. tracks these shifts across Mount Pleasant and the rest of the Lowcountry year-round. Book an appointment if you'd like a resident's-eye read on what's coming next.